WestMinCom Commander Lt. Gen. Corleto Vinluan, Jr., together with 54EBde Commander Brig. Gen. Anthony Cacayuran, checked on the progress of the said project on Monday morning, May 24, 2021.
According to Brig. Gen. Cacayuran, the project commenced on March 13, 2017 in the island municipality of Mapun and it is now 95% completed.
"Currently, we are doing the installation, stringing, and tensioning of Aluminum Conductor Steel Reinforced ( ACSR) wire on the 11 steel poles at Sitio Batutay in Barangay Gupah," said Brig. Gen. Cacayuran.
Target completion of the project is by the end of the 2nd quarter.
A Sangguniang Bayan member said the people of Mapun are very happy and grateful of the support the military is extending to improve their status of living.
Meanwhile, Lt. Gen. Vinluan, Jr. also paid a courtesy call on Municipal Officer-in-Charge Omar Mockthar Abdulpatta on the same day.
On behalf of Mayor Suraida Muksin, Abdulpatta expressed his gratitude to Lt. Gen. Vinluan, Jr. and to the troops deployed in the different barangays of Mapun for maintaining the peace and order in the communities.
Lt. Gen. Vinluan, Jr. lauded the good governance of the local government officials of Mapun."Let us continue to work together for peace and prosperity here in the beautiful island of Mapun," the commander said.
"Rest assured that Team WestMinCom will always be your partner for
development while we continue to sustain the peace in the area," he added.(By JONG CADION with report and photos from WestMinCom-PIO)